2024
Arrival at Astrotech!
On Sunday, August 18, 2024 at around 3 AM, “Betty” Blue and “Goldilocks” Gold arrive at the Astrotech Space Operations processing facility just outside Kennedy Space Center, following a three-day journey across the country from California.

August 18, 2024, unloading at dawn.

Careful with that forklift!

Blue & Gold in their shipping containers & GSE boxes.

Gold TVAC testing complete!

More great work from our Rocket Lab partners and both spacecraft are finished environmental testing!

Blue TVAC testing complete!

Blue, the spacecraft on the left, has completed a successful thermal vacuum test campaign. Meanwhile Gold, the spacecraft on the right, has completed pre-environments testing and is now into vibration testing. Not long to go until these beautiful machines are shipped out to the Cape ready for their journey to Mars!

Shocking Vibes!

Blue spacecraft completed shock & vibe testing at Rocket Lab USA, Long Beach.  Ready for TVAC!

Propulsion System Installation

Our partners at Rocket Lab USA are working hard to integrate the propulsion systems we need to be captured by Mars’s gravity and synchronize our orbits!

ESCAPADE Engine Installation

Project Team Meeting @ Berkeley

The full Science & Project teams met at UC Berkeley on January 29 to provide updates and familiarize all parts of the project with each other as we move into our launch year!!

2023
Pre-Environmental Review (PER)

With the two spacecraft (mostly) assembled, it’s time to carefully review the configuration of the system & ensure that all unit-level, subsystem, and system testing has been completed.  Here is where we make sure everything is ready to put the spacecraft through their environmental tests, i.e. the conditions they will face (vibration, acoustic, vacuum, and thermal) during launch and in space.

Instrument Integration on Spacecraft

Fully tested and delivered, time to mount the instruments on the Blue & Gold Spacecraft and put them through their paces!!

Structural Qualification!

We built up a full copy of the spacecraft to make sure our design can survive the punishing environment of launch into space!

Instruments Come Together!

It’s Instrument Suite I&T! Instrument teams are hard at work assembling, testing, disassembling, cleaning, retesting.  Here’s EESA-e instrument lead Phyllis Whittlesey hard at work.

2022
Critical Design Review

After some challenges over the summer following changing the separation and propulsion systems, the team at UCB and RL completed a successful CDR. From the Independent Review Board:

The Escapade independent Mission CDR demonstrated stunning progress since the Spacecraft CDR in June.  All the actions from SCDR were addressed.   The entire independent review board, as well as the NASA reviewers, were impressed with the professionality and thoroughness of the presentation at this MCDR. This was a fantastic review!

New Propulsion System


New Zealand COVID delays impacted qualification schedule of original system; inadequate time remained to resolve issues found.
Replaced with off-the-shelf solution from Arianne Space.
New design brought up to CDR maturity, peer reviewed

2021
ESCAPADE confirmation

After 8 months of design work with a Rocket Lab USA and successful 2nd PDR, ESCAPADE passes its KDP-C on August 17, 2021, with a new target launch readiness date of May 2024.

NASA press release

Berkeley News article.

Daily Californian article

Rob Lillis Interview with Matt Kaplan on Planetary Radio.

Supercluster article.

2020
Rocket Lab Selected as ESCAPADE Spacecraft Contractor

Press Release: Space company Rocket Lab plans to build new Mars spacecraft

The University of California-Berkeley has chosen California-based space company Rocket Lab to build two spacecraft for one of the least expensive interplanetary missions in history, a scientific investigation of the Martian magnetosphere. Read more.

ESCAPADE demanifested from Psyche launch, Phase B Extension

With Psyche’s launch targets unviable for ESCAPADE, we were removed from the Psyche launch manifest and provided an additional 9 months and $1.8 m to redesign the mission to be as flexible as possible in terms of launch.

Article: ESCAPADE demanifested from Psyche launch

 

Preliminary Design Review

New and very different launch targets for the Psyche mission announced in May 2020 led to a scramble to redesign the ESCAPADE mission in just 2 months, stretching design margins to breaking point.

Result: failed PDR :-(.

2019
System Requirements Review

Before we realized EESA had to be body-mounted

ESCAPADE selection

NASA Planetary Director Lori Glaze calls Rob: ESCAPADE has been selected for Phase A/B study!  

Rob looking goofy in promo video.

Selection Day Videos on Twitter

NASA Press Release

KRON4 Bay Area News

2018
2017
2016